Friday, March 8, 2024

News: 60mph speed limit trial complete on M1 through Rotherham

By

A trial of 60mph speed limits on the M1 in Rotherham to address air quality has been completed.

Rothbiz reported in 2020 that Highways England (now National Highways) was introducing the speed limits as action needed to be taken to reduce emissions and improve air quality.

The limits were made operational 24 hours a day instead of during peak times as they were previously when the M1 all-lane running became operational in the region and open to traffic in 2017. The section was designated as Britain's first ever Air Quality "Speed Limit" based motorway.

The move followed on from 2014, when the then Transport Secretary put the brakes on the agency's plans to implement a maximum mandatory 60mph speed limit in the area.

The expectation for the trials was a reduction in nitrogen dioxide (NO2) when traffic is reduced from 70 to 60mph but Covid 19 lockdowns in 2020 and 2021 and the reduced traffic flows impacted traffic and emissions levels, and National Highways' ability to collect monitoring data.

Advertisement
Monitoring contined after COVID and now the government-owned company charged with operating, maintaining and improving motorways and major A roads in England, say that the speed limit trial between M1 junctions 34 to 33 at Rotherham is complete, "after evidence showed that air quality at these locations has improved."

Initial findings showed that managing speed at 60mph has the most significant impact, reducing emissions on average by 17%, and that the impact on journey times is considered minimal due to the section of the motorway being less than 4.5 miles.

South Yorkshire was identified as a location where NO2 levels exceeded the legal limit annual mean limit level of 40 µg/m³.

Last year the government confirmed that plans for new smart motorways would be cancelled in recognition of the "lack of public confidence felt by drivers and cost pressures." The government and National Highways also said that it would continue to invest £900m in further safety improvements on existing smart motorways.

An emergency area retrofit continues to double the number of emergency areas on the M1 between junction 32 at Thurcroft and junction 35A at Stocksbridge, with 12 new emergency areas being added to the existing eight.

As work is expected to be complete by winter 2024, drivers will have to wait for the return of 70mph limits in the area as the left-hand lane remains closed throughout construction to allow engineers to carry out the upgrade safely. For lanes two, three and four, they remain open with a 50mph speed limit in place.

In December, National Highways confirmed that the stretch of the M1 between junctions 28 to 31 would gain additional emergency areas but no start date for work was given.

National Highways website

Images: National Highways

Read more...

Thursday, April 22, 2021

News: Smart motorways through Rotherham need more measures to make them safe

By

Existing All Lane Running (ALR) motorways are set to have the technology to spot stopped or broken-down vehicles quickly fitted six months earlier than originally planned.

Highways England Smart Motorway schemes through the borough include the scheme on a ten mile stretch of the M1 between junctions 32 (south of Sheffield and Rotherham) and 35a (north of Sheffield and Rotherham) and a 20 mile stretch of the M1 between junction 28 (South Normanton) and 31 (Aston).

The multimillion pound projects include converting the hard shoulder to an extra traffic lane in both directions and variable mandatory speed limits and they deliver benefits at a significantly lower cost than conventional motorway widening, and with less impact on the environment during construction.

A legal case was launched last year after two men were killed when they were knocked down by a HGV near junction 34 of the M1 at Meadowhall. The Government published an action plan last year to boost safety, backed by a £500m investment.

ALR motorways are fitted with technology and features not seen on conventional motorways, such as set-back emergency areas, and red X signs on gantries to close live lanes. Radar detection to spot stopped vehicles is also being rolled out.

To accelerate improvements, by the end of September 2022, Highways England said that it would install radar technology on all existing stretches of ALR motorway, six months earlier than planned, upgrade special cameras ten months earlier than planned, so that they can be used to spot and prosecute motorists ignoring red X signs and illegally driving down closed lanes, putting themselves and others in danger, and install around 1,000 additional approach signs six months earlier than planned, alerting drivers to their nearest place to stop in an emergency.

Every new ALR motorway will open with the technology in place and more measures are expected when further research is complete.

Advertisement
Transport Secretary Grant Shapps said: "Despite the data showing that fatalities are less likely on All Lane Running motorways than on conventional ones, this doesn’t mean all drivers necessarily feel safe on them.

"That is why I tasked Highways England last year with delivering an action plan to raise the bar on safety measures even higher. This progress report shows the extensive work already carried out, but we want to do more.

"Alongside the raft of measures already undertaken, today I am announcing that all new All Lane Running motorways will open with stopped vehicle detection technology in place, as well as a programme to speed up the roll-out of the technology on previously built stretches of All Lane Running motorways to next year. This will help us further reduce the risk of accidents on the country’s roads."

"So-called smart motorways started to be built in 2001 and I am determined to ensure that technology and exacting standards are in place."

Highways England’s Acting Chief Executive Nick Harris added: "I want Highways England to continue to be an organisation that listens and puts the safety of road users first.

"We’ve made good progress delivering the improvements set out in the 2020 stocktake, but we are not complacent and are examining ways to improve safety further.

"We will continue implementing the findings, and will work with drivers to make increasingly busy motorways safer for everyone who uses them."

Claire Mercer from Rotherham, whose husband was killed on the M1, instructed Irwin Mitchell to fight for a judicial review of the decision to allow Smart Motorways to be brought in.

Sarah Champion, MP for Rotherham, welcomed the new technology but added that it "doesn’t address the fundamental problem."

Champion said: "While it can improve safety, in the end, all Highways England and the Government are doing is mitigating to a small degree a risk they themselves have created.

"Highways England continue to disingenuously offset the safety improvement that a managed environment delivers against the risk of removing the hard shoulder. But these are not mutually exclusive. A managed environment can be delivered while keeping the hard shoulder.

"If safety really was the number one priority, then delivering basic safety measures like properly spaced refuges would have been built into the design from the word go. Instead, we must wait two years from the publication of the initial report simply to learn the outcome of a review.

"I am gravely concerned that more lives will be lost whilst we wait. The Government should immediately commit to restore the hard shoulder pending work to install additional refuges. If it’s not be possible to deliver these safely, they should return to traditional operation, with a hard shoulder."

Images: Highways England

Read more...

Friday, September 18, 2020

News: 60mph speed limit on M1 in bid to cut pollution levels in Rotherham

By

Highways England has confirmed that it will trial 60mph speed limits on the M1 in Rotherham as action needs to be taken to reduce emissions and improve air quality.

The limits would be operational 24 hours a day instead of during peak times as they currently are.

The M1 smart motorway became operational in the region and open to traffic in 2017 with the section was designated as Britain's first ever Air Quality "Speed Limit" based motorway.

Highways England completed a £106m scheme on a ten mile stretch of the M1 between junctions 32 (south of Sheffield and Rotherham) and 35a (north of Sheffield and Rotherham), and a 20 mile stretch of the M1 between junction 28 (South Normanton) and 31 (Aston) in a project costing £205m.

The projects include converting the hard shoulder to an extra traffic lane in both directions and variable mandatory speed limits set daily between 7-9am and 3-6pm.

Now Highways England is proposing to introduce speed restrictions in various locations including between M1 junctions 34 (Meadowhall) and 33 (Catcliffe).

Advertisement
An update from the government agency said: "We are testing whether reducing the speed limit reduces NO2 levels. We will continually monitor this trial and if proven successful, the speed limit will remain in place until the area is compliant.

"The locations were identified as locations where NO2 levels exceed the legal limit annual mean limit level of 40 µg/m³.

"We have a duty to bring these locations into compliance with the limit value in the shortest possible time where feasible options exist. In these trial locations we expect that reducing the speed will lead to a reduction in emissions and accelerate compliance."

In 2014, the Transport Secretary put the brakes on the Highways Agency's (now Highways England) plans to implement a maximum mandatory 60mph speed limit. The speed limit would have been used between 7am and 7pm, seven days a week.

Highways England has confirmed that the speed limits will be operational 24 hours a day, adding: "We need to improve air quality at these location in the shortest timeframe possible. Emissions levels are calculated on an annual average basis, and so having the speed limits in place 24 hours a day will bring down the annual averages in the shortest timescale possible. Also vehicles travelling late at night often travel at higher average speeds resulting in high levels of harmful emissions. All vehicles emissions at any time of day contribute to the total."

Reduced speed limits are expected to have a "negligible impact" on journeys as the length of road covered by the limit will be less than 4.5 miles.

Rothbiz reported last week that, having been charged with coming up with local plans for reducing air pollution, Sheffield Council announced that it was delaying its proposals in order to review the possible impacts of COVID-19 on businesses, transport, and air quality.

Highways England website


Images: Highways England

Read more...

Thursday, January 23, 2020

News: Legal case over smart motorways

By

The grieving widow of a driver killed on a smart motorway has instructed specialist lawyers at Irwin Mitchell to begin work on a High Court legal challenge calling for them to be scrapped.

Jason Mercer was one of two men killed when they were knocked down by a HGV near junction 34 of the M1 at Meadowhall in South Yorkshire. Moments earlier Jason, of Rotherham, and 22-year-old Alexandru Murgreanu, from Mansfield, had been involved in a minor collision.

The stretch of road is classed as an all lanes running (ALR) motorway, meaning there is no hard shoulder in operation. Jason, 44, and the other man had pulled over as far as they could to exchange details. However, after they left their vehicles a lorry collided with the pair. They were pronounced dead at the scene.

Their deaths mean that five people have died on that route in the past year.

Highways England schemes through the borough include the £106m scheme on a ten mile stretch of the M1 between junctions 32 (south of Sheffield and Rotherham) and 35a (north of Sheffield and Rotherham) and a 20 mile stretch of the M1 between junction 28 (South Normanton) and 31 (Aston).

The projects include converting the hard shoulder to an extra traffic lane in both directions and variable mandatory speed limits and they deliver benefits at a significantly lower cost than conventional motorway widening, and with less impact on the environment during construction.

Advertisement

Helen Smith, solicitor at Irwin Mitchell, said: "The safety of smart motorways which operate without a hard shoulder has been called into question on a number of occasions in recent years and the number of fatalities on such routes both locally and nationwide is a major cause for concern.

"In fact the Transport Select Committee has previously published a report warning that the government should not go ahead with all lane running motorways because they posed a dangerous risk to drivers and emergency services.

"Through our initial investigations and the increasing amount of families which have been torn apart because of fatalities on smart motorways, it is clear that a full and urgent review of their use needs to be completed."

Leading a Parliamentary debate this week, Rotherham MP Sarah Champion challenged the Government to improve safety on ALR Smart Motorways or face the prospect of more deaths.

She said: "The safety of motorists must always be paramount. It is totally unacceptable to risk lives in the name of cost savings.

"There is no evidence that shows me that ALR can ever be delivered safely. I therefore strongly believe the government must stop the rollout with immediate effect.

"Until the obvious and intrinsic risks which come with removing the hard shoulder are addressed, existing schemes should be revert to traditional motorways from today."

Images: Highways England

Read more...

Wednesday, March 22, 2017

News: Value for money of major transport schemes questioned

By

The Value for Money promised by large Government funded transport schemes like the multimillion pound "Smart Motorway" schemes through Rotherham is at risk, according to a report by the National Audit Office (NAO).

The NAO scrutinises public spending for Parliament and has published a report into the Government's Road Investment Strategy which was published in time for the 2015 election. It concludes that it is an important step towards better long-term planning of England's strategic road network but added that the speed with which it was put together has created risks to deliverability, affordability and value for money which could be carried forward into future road investment periods.

Covering the period 2015 to 2020, the strategy involved investing £15.2 billion in over 100 major schemes to enhance, renew and improve the road network. It included the £106m Highways England scheme to convert the hard shoulder of the M1 through Rotherham to an extra traffic lane in both directions and variable mandatory speed limits.

Work by contractors, Costain, is due to complete by the end of this month on a ten mile stretch of the M1 between junctions 32 (south of Sheffield and Rotherham) and 35a (north of Sheffield and Rotherham). A 20 mile stretch of the M1 between junction 28 (South Normanton) and 31 (Aston) is also benefiting from a smart motorway project costing £205m where four lane running began last year.

The schemes are designed to deliver benefits at a significantly lower cost than conventional motorway widening, and with less impact on the environment during construction.

Advertisement

The NAO said that the Department for Transport planned the Strategy in 17 months, in order to publish it before the May 2015 General Election. As a result of this, the Department selected projects without knowing whether they would be the best value and 54 of the 112 projects are currently scheduled to start in 2019/20, which could cause significant disruption to motorists.

It added that by August 2016, the amount by which forecast capital costs exceeded available funding had increased to £841m at the same time as Highways England being asked to achieve efficiency savings.

As a result, Highways England is now reviewing the portfolio of enhancement projects to improve value for money, and has so far identified 16 projects which present a risk to value for money. Highways England and the Department are exploring a number of ways to manage this risk, including revising project design, cancelling projects or delaying projects to enable further assessment of benefits.

The NAO also warned that the follow up strategy, for the period after 2020, is at risk due to current performance. £8.3 billion has effectively committed to road enhancement projects in from 2020 to 2025. It includes studies into a potential Trans-Pennine tunnel and further Smart Motorway projects in the region.

Highways England has set out proposals for a project for four lane running on a stretch of the motorway between Rotherham and Wakefield which would ultimately help create a smart motorway all the way to Leeds.

In the 2016 budget, the Government confirmed that funding would be made available to accelerate an M1 smart motorway scheme from junction J35a to 39.

Highways England

Images: Highways England


Read more...

Wednesday, August 10, 2016

News: Work continues on Smart Motorway

By

Further "superspan" gantries crossing the M1 will be installed overnight this month as part of a major smart motorway project to tackle congestion and improve journey times through Rotherham.

Highways England has been working on the £106m scheme on a ten mile stretch of the M1 between junctions 32 (south of Sheffield and Rotherham) and 35a (north of Sheffield and Rotherham). A 20 mile stretch of the M1 between junction 28 (South Normanton) and 31 (Aston) is also benefiting from a "smart motorway" project costing £205m where four lane running began in April.

The projects include converting the hard shoulder to an extra traffic lane in both directions and variable mandatory speed limits and they deliver benefits at a significantly lower cost than conventional motorway widening, and with less impact on the environment during construction.

Costain, contractors for Highways England will be installing the gantries overnight, between 9pm and 6am, starting on Monday August 15.

The first two gantries will be installed overnight on Monday August 15 and on Tuesday August 16 between junction 33 (Catcliffe) and junction 34 (Meadowhall).

Advertisement

To carry out the work lanes two and three on the northbound carriageway and all three lanes on the southbound carriageway will be closed, with traffic travelling on the hard shoulder. Traffic will be temporarily stopped while the lift is undertaken.

A further six gantries between junctions 32 and 33 will be installed over four nights starting on Monday August 22. The southbound carriageway will be fully closed along with lanes two and three on the northbound carriageway.

Arun Sahni project manager at Highways England, said: "The erection of a "superspan" is a big job that calls for overnight closures, but then they're very big structures. You really get a sense of their size when they are on the ground waiting to go up.

"While we have the closures in place for the six nights we will also be carrying out other works in the area which included resurfacing of the entry slip road at junction 33."

Work on the 32 - 35 stretch is scheduled to complete "by the end of March 2017."

Environmental assessments carried out on the managed motorway schemes through the Sheffield city region showed there was likely to be an adverse impact on local air quality if the motorway continued to operate at the national speed limit (70mph).

A proposed maximum mandatory 60mph speed limit was discounted by the Government and the latest option could see 60mph speed limits at weekday peak times between junctions 28 and 35a - between 07:00-09:00 in the morning and 15:00-18:00 in the evening.

The Transport Committee of MPs recently warned that the Government should not proceed with "all lane running" schemes while major safety concerns exist.

Highways England website

Images: Morgan Sindall


Read more...

Monday, June 20, 2016

News: M1 closure for smart motorway upgrade

By

A "superspan" gantry crossing the M1 will be installed overnight tonight as part of a major smart motorway project to tackle congestion and improve journey times through Rotherham.

Highways England has been working on the £106m scheme on a ten mile stretch of the M1 between junctions 32 (south of Sheffield and Rotherham) and 35a (north of Sheffield and Rotherham). A 20 mile stretch of the M1 between junction 28 (South Normanton) and 31 (Aston) is also benefiting from a "smart motorway" project costing £205m where four lane running began in April.

The projects include converting the hard shoulder to an extra traffic lane in both directions and variable mandatory speed limits and they deliver benefits at a significantly lower cost than conventional motorway widening, and with less impact on the environment during construction.

Costain, contractors for Highways England will be installing the overhead gantry, which will carry message and variable speed limit signs, on Monday night when traffic levels are at their lowest.

The gantry – which will span both the northbound and southbound carriageways of the motorway – is approximately 47 metres wide, weighs up to 30 tonnes and will require a special 200 tonne crane to help install it as well as an overnight closure of the northbound carriageway. One lane will remain open on the southbound carriageway.

Advertisement

The gantry will be erected between junction 35 at Rotherham and junction 36 at Barnsley overnight between 9pm and 6am. The closure could be postponed if strong winds are forecast.

Arun Sahni, project manager at Highways England, said: "The erection of a "superspan" is a big job that calls for a night closure on the northbound carriageway, but then they're very big structures. You really get a sense of their size when they are on the ground waiting to go up.

"This gantry is also close to an overhead electric cable which is why we need to close the carriageway, so it's important for people who use the motorway at night to plan their journeys."

Work on the 32 - 35 stretch is scheduled to complete "by the end of March 2017."

Environmental assessments carried out on these proposed managed motorway schemes showed there was likely to be an adverse impact on local air quality if the motorway continued to operate at the national speed limit (70mph).

A proposed maximum mandatory 60mph speed limit was discounted by the Government and the latest option could see 60mph speed limits at weekday peak times between junctions 28 and 35a - between 07:00-09:00 in the morning and 15:00-18:00 in the evening.

Highways England is looking at other mitigation options and conculded at the end of last year: "Imposing speed control will only be used as a last resort. A number of automatic air quality continuous monitors have been installed alongside the M1 and data from these continuous monitors will be used to evaluate the mitigation measures and the date when the measures can be lifted."

Highways England website

Images: Costain

Read more...

Friday, April 8, 2016

News: First Rotherham smart motorway scheme completes

By

Four lane running has begun on a stretch of the M1 motorway through Rotherham as part of a £205m project to deliver better and smoother journeys, helping businesses and boosting the local economy.

Highways England has been working on the scheme on a 20 mile stretch of the M1 between junction 28 (South Normanton) and 31 (Aston). A ten mile stretch of the M1 between junctions 32 (south of Sheffield and Rotherham) and 35a (north of Sheffield and Rotherham) is also set to benefit from a "smart motorway" project costing £106m.

The projects include converting the hard shoulder to an extra traffic lane in both directions and variable mandatory speed limits and they deliver benefits at a significantly lower cost than conventional motorway widening, and with less impact on the environment during construction.

Costain, the contractors for Highways England, have worked 1.75 million combined hours to complete the first scheme, which will improve journeys for more than 95,000 drivers a day using this stretch.

A similar scheme on the M25 which opened just over a year ago has seen the busiest journey times being halved and the number of collisions reduced by a fifth.

Advertisement

Andy Kirk, senior programme manager at Highways England, said: "The new smart motorway will tackle congestion and improve journey times for the thousands of drivers who use it every day.

"The hard shoulder has been permanently converted to an extra lane to significantly increase capacity, and we'll keep vehicles moving using variable speed limits.

"We'd also like to thank drivers for their co-operation during the work and look forward to improving journey times for those travelling between the East Midlands and South Yorkshire."

Richard Stuart, project director at Costain, added: "It has involved high levels of collaboration between the project team, Highways England internal stakeholders and many external stakeholders. Despite numerous challenges along the way, the project has stood out for the one-team spirit which has underpinned the successful delivery through industry leading production rates, innovation and skills development. Of particular note is the holistic approach that the team has taken to the improvement works, with significant additional maintenance and asset renewals works delivered through the scheme to make most efficient use of the team’s presence on the network."

CCTV will be used 24 hours a day to enable staff in Highways England's regional control centres near Nottingham and Wakefield to respond quickly to incidents, closing lanes using red "X's" on overhead signs if necessary.

Drivers using the upgraded stretch of the M1 will also be able to use emergency refuge areas if they break down.

Work continues on the 32 - 35 stretch with construction scheduled to complete "by the end of March 2017."

Environmental assessments carried out on these proposed managed motorway schemes showed there was likely to be an adverse impact on local air quality if the motorway continued to operate at the national speed limit (70mph).

A proposed maximum mandatory 60mph speed limit was discounted by the Government and the latest option could see 60mph speed limits at peak times between junctions 28 and 35a. Highways England is looking at other mitigation options and imposing speed control will only be used as a last resort.

Highways England has set out proposals for a project for four lane running on a stretch of the motorway between Rotherham and Wakefield which would ultimately help create a smart motorway all the way to Leeds. In the recent budget, the Government confirmed that funding would be made available to accelerate an M1 smart motorway scheme from junction J35a to 39.

Highways England website

Images: Costain

Read more...

Wednesday, October 7, 2015

News: Smart motorway moves on

By

The next stage in creating smart motorways through Rotherham gets underway this week.

A ten mile stretch of the M1 between junctions 32 (south of Sheffield and Rotherham) and 35a (north of Sheffield and Rotherham) is set to benefit from a project costing between £100.2m and £142.1m. A similar scheme costing between £168m and £225m is being carried out on the M1 between junction 28 (South Normanton) and 31 (Aston).

The projects include plans for converting the hard shoulder to an extra traffic lane in both directions and variable mandatory speed limits and they deliver benefits at a significantly lower cost than conventional motorway widening, and with less impact on the environment during construction. Signs and signals will still be used to inform drivers of conditions on the network and when variable speed limits are in place.

As part of the project, the latest technology is being installed to monitor traffic levels, provide traffic information to road users, and ease congestion by using variable speed limits on overhead message signs.

The hard shoulder is also being permanently converted into an extra lane between junction 32 at Rotherham and junction 35a at Stocksbridge to provide extra capacity.

Andy Kirk, senior project manager at Highways England, said:"Work on the scheme is progressing well and we are now in a position to start the work between junctions 32 and 34. Narrow lanes are being introduced along the route and a 50mph speed limit is in place for the safety of workers and drivers.

When complete, road users will benefit from reduced congestion and more reliable journey times as a result of the hard shoulder being converted to an extra lane and variable mandatory speed limits being used to keep traffic moving."

Roadworks have already been lifted between junctions 30 and 31 along the M1 as part of another smart motorway scheme. And roadworks are due to be removed between junctions 29a and 30 later this month.

Costain, the engineering solutions provider, recently moved from Markham Vale and took on the former Sterecycle site at Templeborough in Rotherham whilst it carries out work on the M1. It secured contracts worth around £125m to carry out work on the two schemes.

In its next "Road Period" which begins in 2019/20, Highways England detailed a further 15 planned investments. This includes a project for four lane running on a stretch of the motorway between Rotherham and Wakefield which would fill in the gap and ultimately create a smart motorway all the way to Leeds. With 41 lane miles set to be converted with schemes underway, the next project would provide an additional 27 lane miles of capacity.

The long term goal is a smart motorway spine linking London, Birmingham, Manchester and Leeds.

Highways England website

Images: Highways England

Read more...