News: Whitestone - the £600m planned investment in Rotherham that would create just 39 long term jobs

By

Planning documents for one of the largest solar farms in the country have been published - all 159 of them.

Rothbiz reported last year on early stage plans being updated for Whitestone Solar Farm - a generating station with an estimated capacity of up to 750MW connecting to the National Grid Brinsworth Substation in Rotherham.

Whitestone has been given a cost estimate of between £500m and £600m. It is being promoted by Green Nation but operates under Net Zero One Ltd.

Initial consultation documents from Green Nation showed that vast areas of agricultural land in Rotherham and Doncaster, some safeguarded for the now-cancelled HS2 route, could make up the solar farm.

The northern site straddles the Rotherham and Doncaster border east of Hooton Roberts and north of Ravenfield.

Farmland adjacent to the M18 south of Bramley and Wickersley has also been identified to host thousands of solar panels, as has vast areas of fields either side of the M1 south of its junction with the M18. This includes sites near Ulley, Aston and Brampton, out towards North and South Anston, and the other way to land between Treeton and Whiston.

In the south of the borough, sites that are included in the proposed solar farm development are close to Kiveton Park, Harthill and Woodall.

Whitestone is classified as a Nationally Significant Infrastructure Project (NSIP), which means that it is applying for a Development Consent Order (DCO) to authorise its construction, operation and decommissioning. The final decision on a DCO application will be made at the national level by the Secretary of State for Energy Security and Net Zero.

A three month pre-examination stage has now begun looking at the issues which will need to be discussed at the examination stage. This next stage is where the applicant, anyone who is registered to have their say, official bodies and people whose land is directly affected can comment on the proposed development or answer any of the questions at each deadline.

Advertisement
Documents include numerous environmental statements on things like Landscape and Visual Impact (LVIA), contaminated land and transport, plus outline strategies for landscape and ecology management, surface water drainage and Public Right of Way (PROW) management.

However, much of the details are not yet known. Developers want to "maintain flexibility in the design" and instead specify parameter ranges, including details of the maximum, and minimum, size (footprint, width, and height, technology,) and locations of the different elements of the proposed development.

Plans also show that the developers are enacting a compulsory acquisition of land.

Applicants also say that they are proposing a large scheme due to its bulk generation potential and connection to the national grid that means that benefits are felt more widely. It discounts brownfield and rooftop sites due to thier unsuitability and related "ownership, occupation, and upkeep" issues.

On employment, planning documents say that: "During construction, it is anticipated that there would be 1,616 FTE jobs created as a result of direct, indirect and induced employment opportunities and that 538 of these would be from the local Study Area. Once operational, impacts on local labour market arising from operational and maintenance jobs would be more limited but still present, with 39 FTE direct, indirect and induced jobs created."

Promoters of the scheme, which they want to operate for 60 years, say that the proposed development is located on "grey belt land because the site does not strongly contribute to Green Belt purposes" but go on to say that "even if this position is not accepted, there are Very Special Circumstances that clearly outweigh any harm identified in terms of the five Green Belt purposes."

The applicants conclude: "The significant need for low carbon electricity generation infrastructure to meet the government’s decarbonisation objectives, and wider environmental benefits of the proposal, including the significant increase in BNG and creation of new permissive paths locally, would outweigh any harm identified to the Green Belt."

Rotherham Council does not agree that the site is "grey belt" stating that "this part of the Borough performs an important strategic and local function as open countryside in a relatively densely populated area, helping to maintain separation between settlements, prevent encroachment into the countryside and preserve a sense of openness."

Rotherham Council and the local MPs have raised issues with the scheme's consultation.

Rothbiz has detailed the issues raised by Rotherham Council with the Whitestone proposals.

Whitestone website

Images: Pexels / Giant Asparagus

Read more...

Thursday, April 24, 2025

News: Plans updated for massive solar farm in Rotherham

By

Following consultation, early stage plans have been updated for a massive solar farm that could take up acres of green belt land in Rotherham.

Rothbiz reported at the end of 2024 on plans for Whitestone Solar Farm, which if constructed, would generate up to 750MW of energy, enough to power up to 250,000 homes.

Consultation documents from solar developer Green Nation showed that vast areas of agricultural land in Rotherham and Doncaster, some safeguarded for the now-cancelled HS2 route, could make up the solar farm.

The northen site straddles the Rotherham and Doncaster border east of Hooton Roberts and north of Ravenfield.

Farmland adjacent to the M18 south of Bramley and Wickersley has also been identified to host thousands of solar panels, as has vast areas of fields either side of the M1 south of its junction with the M18. This includes sites near Ulley, Aston and Brampton, out towards North and South Anston, and the other way to land between Treeton and Whiston.

In the south of the borough, sites could be included in the solar farm development that are close to Kiveton Park, Harthill and Woodall.

Having recently completed a first consultation stage, developers say that they have made "significant changes to the project design" to respond to the feedback received.

Updated documents explain that one fourth of the land (279 hectares / 689 acres) has been removed across the whole site that was included for solar development to create buffers around homes, villages and public rights of way near the project boundary. This has resulted in the removal or reduction of panels around the most sensitive community areas, particularly around residential dwellings.

Developers say that: "These areas would not have any solar panels or other above-ground infrastructure. Some will now be set aside for environmental enhancement and mitigation, and would be planted with a mix of native grasses and wildflowers to support wildlife and increase biodiversity."

The area for solar development and associated infrastructure would now only account for around half of the total updated site area.

Advertisement
Whitestone is classified as a Nationally Significant Infrastructure Project (NSIP), which means that it would go for a Development Consent Order (DCO) to authorise its construction, operation and decommissioning. The final decision on a DCO application will be made at the national level by the Secretary of State for Energy Security and Net Zero.

A scoping seport is being submitted to the Planning Inspectorate. This enables the project to be designed to avoid or minimise negative environmental impacts and provides an opportunity to incorporate positive environmental enhancements into the project. A formal application is not expected until the summer of 2026.

Green Nation is planning a second consultation this autumn based on the updated proposals and the preliminary results of the environmental assessments.

The developers said: "During this consultation, which will be considered ‘statutory’, we will consult with the community, elected officials, and technical experts to fact check our initial results and help inform the final assessments that we will submit in our DCO application. When we get closer to the autumn, we will notify the community of the details of the consultation and how you can take part."

Jake Richards, MP for Rother Valley, who has already raised concerns about the proposals, said of the update: "I am pleased that this has resulted in some significant changes and a 25% reduction in the scale of the plan. It is welcome that particular areas which local residents sought to be protected have been.

"But nonetheless, the revised plan is not good enough. Whilst I support the government’s plans for more renewable energy to cut bills and end our reliance on foreign supplies, my priority is always my constituents. Residents in the affected areas - Harthill, Woodall, Aston, Brampton-en-le-Morthen and Ulley – are rightly worried about this and I will stand with them.

"I will continue to work with the developer, urging them to make further changes."

Whitestone Solar Farm website

Images: Google Maps

Read more...

Friday, December 6, 2024

News: Rother Valley MP "really concerned" over huge solar farm plans

By

Jake Richards, MP for Rother Valley, has met with the company that has started consultation on early stage plans for a massive solar farm that could take up acres of green belt land in Rotherham.

Rothbiz reported last month on Whitestone Solar Farm, which if constructed, would generate up to 750MW of energy, enough to power up to 250,000 homes.

Consultation documents show that vast areas of agricultural land in Rotherham and Doncaster, some safeguarded for the now-cancelled HS2 route, could make up the solar farm. Sites in the Rother Valley constituency include fields near to Bramley and Wickersley, near Ulley, Aston and Brampton, out towards North and South Anston, and close to Kiveton Park, Harthill and Woodall.

Solar developer Green Nation has begun consultation on the scheme that would be classed as a Nationally Significant Infrastructure Project (NSIP) and would not be determined by Rotherham Council, instead a Development Consent Order (DCO) application would be decided at the national level by the Secretary of State for Energy Security and Net Zero.

Advertisement
Jake Richards MP, said: "This week, I met with the developers to find out more about the proposal, which is still at a very early stage. The proposal is not finalised and there has been no application to the Secretary of State.

"However, even at this early juncture I’m really concerned about this project. Whilst we need local energy infrastructure, the sheer scale of what is currently being proposed and the location of some of the sites is worrying. The application is not for me to allow or refuse, but I want to shape it and put pressure on the company to ensure it is done right, if it has to be done. This means we need to protect local green spaces, minimise disruption and invest in the local area. If they do not do this, I will oppose it."

In-person consultation events have begun and online consultation continues to January 17 2025.

Developers explained: "During this period, we are presenting our early proposals and asking for your feedback. This feedback, along with the results of ongoing environmental and technical assessments will help inform the updated project design that we present for our second round of consultation next year."

Whitestone Solar Farm website

Images: Google Maps

Read more...

Monday, November 25, 2024

News: Acres of Rotherham green belt eyed up for massive solar farm

By

Thousands of acres of green belt land in Rotherham has been identified in early stage proposals for the largest solar farm in Yorkshire - and one of the largest in the UK.

Solar developer Green Nation has begun consultation on plans to develop a solar and energy storage scheme that would be classed as a Nationally Significant Infrastructure Project (NSIP).

If constructed, Whitestone Solar Farm would generate up to 750MW of energy, which is enough to power up to 250,000 homes.

Whitestone would dwarf the Common Farm Solar project in Rotherham that secured planning permission in 2023 that would have an installed capacity of up to 50MW (and cover 285 acres with solar panels).

Consultation documents show that vast areas of agricultural land in Rotherham and Doncaster, some safeguarded for the now-cancelled HS2 route, could make up Whitestone Solar Farm.

Advertisement
The northen site straddles the Rotherham and Doncaster border east of Hooton Roberts and north of Ravenfield.

Farmland adjacent to the M18 south of Bramley and Wickersley has also been identified to host thousands of solar panels, as has vast areas of fields either side of the M1 south of its junction with the M18. This includes sites near Ulley, Aston and Brampton, out towards North and South Anston, and the other way to land between Treeton and Whiston.

In the south of the borough, sites could be included in the solar farm development that are close to Kiveton Park, Harthill and Woodall.

The developers say that the sites were chosen as there was available capacity at the Brinsworth substation in Rotherham - a remnant of the area's historic role in steel production.

Green Nation says that it has been able to secure an agreement for a new energy project to connect at this location.

A Battery Energy Storage System (BESS) and cable infrastructure would aslo be required.

With a capacity over 50MW, the plans for the development would not be determined by Rotherham Council, instead a Development Consent Order (DCO) application would be decided at the national level by the Secretary of State for Energy Security and Net Zero.

Classed as temporary (60 years), the proposed solar farms would be designed with open spaces around and between the panels with wildflowers and native grasses planted beneath. Measures are included to reduce the visual impact from homes and public rights of way.

Consultation documents state: "Whitestone could make a significant contribution to our national energy goals – helping in the fight against climate change while also contributing to energy security and helping reduce energy costs by producing clean, renewable energy here in the UK.

"We are at a very early stage in the development of Whitestone. Our goal is to develop the project in a way that is sensitive to the local environment and community. Over the next few months, we will consult with local residents and technical experts to ensure that valuable local knowledge is built into our proposals."

Consultation runs until to January 17 2025 with a number of in person events scheduled, starting in Rotherham at Aston cum Aughton Leisure Centre on November 30.

Developers plan to submit its application in spring 2026 with construction to follow in 2027 and connection in 2029.

Whitestone Solar Farm website

Images: Green Nation

Read more...